北京地铁技术规格书
第二章 专用技术要求
Special Technical Requirement

Table of Contents
1系统基本技术及主要技术指标要求Basic Technology and Key Technical Index of the System
1.1基本技术要求Basic Technical Requirement
1.1.1北京地铁8号线二期工程正线信号系统采用完整的ATC列车自动控制系统,包括列车自动监控子系统ATS、列车自动防护子系统ATP、 列车自动运行子系统ATO三个子系统。本工程信号系统考虑与北京地铁8号线一期工程信号系统的衔接,系统结构及功能采用与一期工程的信号系统相兼容的设备配置,且性能至少达到与一期相同的水平。
The mainline SIG system for BJL8 Phase 2 project uses complete automatic train control (ATC) system, including ATS, ATP and ATO subsystems. SIG system for this project shall con
sider the connection with that for BJL8 Phase 1 project, the equipment with minimum same performance, compatible system structure and function as that of SIG system for Phase 1 project shall be used.
1.1.2由于本工程为一期延伸线工程,与一期线路一体化贯通运行,二期工程信号系统运用方式与8号线一期相一致。北京地铁运营时间
Since this project is the extension of Phase 1 project, it shall be integrated and linked with phase l lines, and the application of SIG system for Phase 2 project shall be same as that for BJL 8 Phase 1 project.
1.1.3本工程信号系统由正线列车自动控制(ATC)系统和车辆段信号设备组成,该系统与一期工程信号系统相互兼容,并能与一期信号系统进行有效的衔接及整合,从而满足与一期工程贯通运营的要求。
SIG system for this project comprises ATC system and depot signaling equipment, the system shall be compatible with SIG system for Phase 1 project and be able to be linked and integrated with SIG system for Phase 1 project so as to meet the requirement for linked operation with Phase 1 project.
1.1.4本工程信号系统实现与一期工程信号系统的无缝衔接及贯通运营。卖方承诺在对一期工程改造、衔接期间不中断一期工程的运营,以及不影响10号线一期的正常运营。
SIG system for this project shall achieve the seamless connection and linked operation with that for phase 1 project. The Seller shall fulfill the none operation stop transition of Line 8 phase 1, as well as no influence to Line 10 phase 1 oepration.
1.1.5本工程信号系统考虑与10号线的分离,卖方提供详细的两线分离的设计方案及实施方案并负责实施,方案需考虑8号线和10号线同期实施及不同期实施两种情况。
SIG system for this project shall consider the separation from line 10, and the Seller shall provide detailed design plan and implementation plan for separation of the two lines. The plan shall include two situations: 1. Line 8 and Line 10 are implemented at the same time, 2. Line 8 and Line 10 are implemented in different time.
1.1.6卖方负责实现8号线全线(包括一期和二期)与TCC系统的接口,包括涉及的一期工程设备编号及接口协议等的相关改造。
The Seller is responsible for realizing the interface between the whole line 8 (including pha
se 1 and phase 2) and the TCC system, including relevant reconstruction of phase 1 project equipment number, interface protocol, etc.
1.1.7本工程新建控制中心,维修中心,一期设备需纳入本中央系统进行控制管理,卖方根据一期工程的实际情况提出详细的改造方案。一二期的系统设备满足安全性、可靠性、可用性和兼容性等技术指标要求,同时具有较高的性能价格比。
This project contain new OCC,maintenance ceter,equipment for phase 1 should be included in the central system to do control and management.the Seller shall present detailed reconstruction plan based on the actual condition of Phase 1 project. Phase 1 and phase 2 equipments shall meet the technical index on safety, reliability, availability and compatibility and shall be of higher cost performance.
1.1.8本工程中卖方提供的设计方案和实施方案均考虑到与8号线分离前与10号线一期工程衔接连续运营的特殊情况,以不中断一期运营为前提。
The design plan and implementation plan of this project provided by the Seller shall consider the special situation of the continuous line operation of BJL10 phase 1 project until separation of BJL8, and consider none operation stop of phase 1.